May 11, 2016

Despite lawsuits against ART, water lines being moved

Albuquerque Rapid Transit sign in downtown Albuquerque

The traffic jams that many predicted would come with Mayor Richard Berry’s Albuquerque Rapid Transit project have already begun, even though two lawsuits have been filed to stop the project.

Albuquerque Rapid Transit sign in downtown Albuquerque

Albuquerque Rapid Transit sign in downtown Albuquerque

The Albuquerque Bernalillo County Water Utility Authority began relocating water lines Tuesday and Wednesday on opposite ends of Central Avenue in anticipation of ART construction.

 Work at Central and Old Coors Road on the West Side began Tuesday, and work at San Mateo and Central on the East Side began Wednesday, said ABCWUA spokesperson Patti Watson.

This originally ran in the ABQ Free Press

The work at both locations has traffic on Central and its cross streets reduced to one lane in one direction. At San Mateo and Central, eastbound traffic on Central was funneled to one lane for at least four blocks west of San Mateo. And southbound traffic on San Mateo was cut to one lane for four or five blocks north of Central.

“The Water Utility Authority is relocating water lines that are in conflict with the proposed ART project, and the criteria is if they are old and they might break during construction. More of them will be coming in the future,” Watson said.

The first two line relocations will cost $1 million to $1.5 million and will last at least 60 days, Watson added. At Central and San Mateo, construction crews are replacing and moving 800 feet of water lines on the south side of Central east and west of San Mateo.

The water line relocations began even though two lawsuits have been filed to stop ART. The complaints, filed in early April in federal state courts, allege that the Federal Transit Administration violated the National Historic Preservation Act and the federal Administrative Act in approving $69 million in federal grants for ART. Both lawsuits seek injunctions to stop ART.

The attorneys who filed the lawsuits were not immediately available for comment.

One of the plaintiffs in the state court suit, Maria Bautista, said the relocation work was sneaky. “It is very underhanded to use the water authority as an excuse to start the ART project ahead of schedule,” Bautista said.

Elizabeth Vencill, an attorney with an office on Quincy Street a block north of Central, said she received no notice work was starting. “It’s basically the city thumbing their nose at the Litigants,” she said.

“The whole thing stinks with so many back-door deals,” Vencill said.

Construction on ART was originally scheduled to start in late May, but was then moved to August.

Author