NMMI records detail numerous construction delays in Mick Rich project

Mick Rich’s slogan for his U.S. Senate campaign is “Send a hard hat to Washington.” Like many candidates, Rich promotes his day job and business skills to show he’s the best choice to represent New Mexicans in the U.S. Senate. His background in major construction projects and his support for the military and national laboratories, […]

NMMI records detail numerous construction delays in Mick Rich project

Mick Rich’s slogan for his U.S. Senate campaign is “Send a hard hat to Washington.” Like many candidates, Rich promotes his day job and business skills to show he’s the best choice to represent New Mexicans in the U.S. Senate. His background in major construction projects and his support for the military and national laboratories, Rich has said, qualifies him to represent the state.

But records from the New Mexico Military Institute (NMMI) show friction between Rich’s contracting company and school officials over a project that should have been finished last year, but still has pending work to be done.

When NM Political Report first asked about the contentious emails and letters, a school official downplayed the delayed project. Rich, however, blamed poor planning from the project’s architect, engineer and school officials for the delay.

A year behind schedule

In December of 2016, a month after President Donald Trump won the election and several months before the 64-year old Rich announced plans to run against incumbent U.S. Sen. Martin Heinrich, NMMI awarded Mick Rich Contractors a $3.1 million contract to renovate the historic Marshall Hall, which houses the campus police department and infirmary. Built in 1920, Marshall was set for its first major overhaul in almost 100 years, according to the school. NMMI is a military preparatory school that also houses students, whose ages range from 14 to 22.

Funding for the renovation mostly came from a general obligation bond approved by local voters, and the project was scheduled to be completed by October 2017.

Four months after the job was scheduled to be  done, NMMI issued a letter requesting a meeting with Rich and notifying Mick Rich Contractors that the school was considering terminating the contract and finishing the job themselves.

“Due to the continued unsatisfactory corrective action of our reported service failures, NMMI is considering terminating the Agreement for cause,” wrote NMMI Chief Financial Officer Scharmer.

According to detailed records from NMMI the school and Mick Rich Contractors agreed during the meeting that the project would be completed by March 2018 and work continued under the original contract.

But the firm missed that deadline, too.

In April, the school notified the project’s bonding company, which essentially insured the project, that NMMI was on the verge of claiming “Contractor Default.” For a second time, NMMI and Mick Rich Contractors agreed to a new deadline, this time in June 2018.

This deadline came and went, though NMMI was able to partially occupy the space by July 2018 to start preparing for the new school year.

In August, 10 months after the original deadline, the surety company that issued the bond for the project asked for an update. In response, NMMI issued a letter outlining what officials saw as months of missed deadlines. The school, for the third time, said Mick Rich Contractors had missed an agreed upon deadline and was in default.

‘A stinkin’ mess’

NM Political Report reviewed hundreds of pages of emails, contract documents and meeting notes related to the Marshall Hall project. Those records detailed the numerous meetings and emails regarding a project that is currently a year past the original completion date.

In at least one instance Mick Rich Contractors’ project manager claimed the company had already asked for more time, a request she said, the school did not honor.

When additional work is requested or a contractor needs more time to finish a project it is common practice in the construction industry to use change orders to document deviations from the original plan.

The records NM Political Report reviewed contained numerous change orders, but none with an adjusted completion date.

In an email to the school’s facility manager, NMMI Chief of Staff Col. David West disputed the project manager’s claim.

“I’m sure she / they will be able to provide proof of the written request for additional time on all 30 [change orders] and the written denial by NMMI(sarcasm),” West wrote, with his own emphasis.

In an initial interview with NM Political Report, West downplayed the delayed contract and said it wasn’t unheard of for projects to take longer than planned.

But when asked about the numerous missed deadlines and letters suggesting his company had defaulted, Rich took a different tone.

“What a stinkin’ mess that job was,” Rich said.

He had choice words for both the project engineer and architect.

“They screwed it up, they put it in our goddamn lap,” Rich told NM Political Report. “I’m really hot over this one.”

He cited more than 70 separate, unforeseen problems his team came across that he said could have been avoided if the project’s architect and school officials had done their due diligence.

“I had multiple conversations down there, and I had a conversation with the general,” Rich said. “I told him, ‘The architect did a God-awful job. The engineer was even worse. Your team didn’t do an adequate job before we got to the project.’”

But, Rich said, he was willing to take on some of the responsibility.

“My team screwed up, we should have made it very clear from day one that we wanted time extensions for all the delays,” Rich said.

Still, Rich insists that thanks to poor planning and project sketches, his workers were unaware of certain problems like walls that were supposed to be demolished but were actually integral to the building’s structure.

“We had one problem after another, one load bearing wall after another,” Rich said.

The architecture firm for the project declined to comment for this story.

Rich’s assertions are backed by a September 2018 letter he sent to the school, contesting the claim that his company defaulted.

“There are 73 documented unforeseen site conditions, which generated 63 change orders for additional work requested by the Architect, but no time extensions were acknowledged,” the letter from Mick Rich Contractors read. “MRC proceeded with work to ensure that the construction progress was not stopped.”

After NM Political Report spoke with Rich about the letters of possible default, his company sent another, more pointed letter to NMMI officials.

“MRC received a copy of [NMMI Director of Facilities] Kent Taylor’s letter to the Western Surety Company regarding the above-referenced project from a third party, and we take exceptions to the statements within,” the new letter read.

The letter also accused an unknown “someone” at NMMI of “turning this issue into a political football.”

But West refuted the claim that NMMI would drag the issue into the political sphere.

“We’re not into the politics,” West said. “Frankly we work for all sides and we’re a state entity.”

Further, West said, Rich’s claims in his letters are based on Rich’s own opinion.

“We developed a letter that we believe is based on facts and not the rancor of the letter that he sent to us,” West said. “He’s certainly welcome to his opinion, but we stand by our letter.”

West, who would not speak on behalf of the project architect, hinted that Rich’s claims that project drawings and planning were partially to blame for the delayed project, is not based in fact either.

“Unfortunately, I think that’s his claim,” West said. “I recognize his claim, but it doesn’t mean we agree with it.”

But delays and default letters aside, the project started off with a $3.1 million price tag and as the end nears, the final cost is $3.4 million, meaning the cost increased by about seven percent. And Mick Rich Contractors is still on the job, which the school estimates has about $65,000 worth of work remaining, or about one percent of the original cost.

West told NM Political Report the school will likely take over the finishing touches, or about $10,000 worth of work.

We're ad free

That means that we rely on support from readers like you. Help us keep reporting on the most important New Mexico Stories by donating today.

Related

Effort to challenge six laws enacted last year comes to an end

Effort to challenge six laws enacted last year comes to an end

Earlier this month, the New Mexico Supreme Court denied and dismissed the effort to challenge six laws enacted in 2023. The New Mexico Supreme…
Governor to call special session for public safety legislation this summer

Governor to call special session for public safety legislation this summer

Gov. Michelle Lujan Grisham announced that she will call the Legislature into a special session this summer to address public safety legislation that did…
Emily’s List endorses seven candidates for Legislature

Emily’s List endorses seven candidates for Legislature

Emily’s List, a nonprofit that supports women candidates and reproductive rights, endorsed seven incumbents facing general election opponents in New Mexico legislative elections. All…
Nuclear Watch New Mexico calls for comprehensive plutonium cleanup at LANL

Nuclear Watch New Mexico calls for comprehensive plutonium cleanup at LANL

A group of anti-nuclear activists used data from Los Alamos National Laboratory to map places where plutonium contamination has been found in areas near…
Fish and Wildlife Service faces new deadline to finalize protections for a NM chipmunk

Fish and Wildlife Service faces new deadline to finalize protections for a NM chipmunk

The U.S. Fish and Wildlife Service has until August 15 to issue a final listing determination for the Peñasco least chipmunk. A federal district…
Ozone pollution continues to plague New Mexico

Ozone pollution continues to plague New Mexico

Four of the nine New Mexico counties evaluated in the annual State of the Air report received failing marks for ozone pollution. The counties…
Amid new graduation requirements, what do high schoolers want to learn?

Amid new graduation requirements, what do high schoolers want to learn?

By Margaret O’Hara, The Santa Fe New Mexican The main things that bring Brayan Chavez to school every day: Seeing, talking to and engaging with…
Special ed teachers hope lawmakers OK pay raises, admin changes

Special ed teachers hope lawmakers OK pay raises, admin changes

By Margaret O’Hara, The Santa Fe New Mexican Brittany Behenna Griffith has a laundry list of adjectives to describe the ideal special education teacher:…
Lawmakers must find consensus on competing education spending plans

Lawmakers must find consensus on competing education spending plans

By Margaret O’Hara, The Santa Fe New Mexican A challenging task awaits New Mexico lawmakers in the next 30 days: Reconciling three very different…
Health workers fear it’s profits before protection as CDC revisits airborne transmission

Health workers fear it’s profits before protection as CDC revisits airborne transmission

Amy Maxmen, KFF Health News Four years after hospitals in New York City overflowed with covid-19 patients, emergency physician Sonya Stokes remains shaken by…
Lujan Grisham, Biden admin announce $10 million in federal funds for tribes, pueblos

Lujan Grisham, Biden admin announce $10 million in federal funds for tribes, pueblos

Gov. Michelle Lujan Grisham announced Friday $10 million in funding from the federal American Rescue Plan Act was awarded to six tribal nations and…
Proposal to curb executive powers moves to House Judiciary

Proposal to curb executive powers moves to House Judiciary

The House Government, Elections and Indian Affairs Committee discussed a potential constitutional amendment that seeks to limit the governor’s executive powers. The committee approved…
Latest SCOTUS abortion case uncertain and could impact New Mexico

Latest SCOTUS abortion case uncertain and could impact New Mexico

The U.S. Supreme Court heard oral arguments on Wednesday on an abortion-related case, this time over whether an Idaho anti-abortion law preempts a federal…
Abortion fund provider rebrands and holds open house

Abortion fund provider rebrands and holds open house

An abortion fund provider unveiled a rebrand and offered an open house in Las Cruces to celebrate the organization’s new name, mission and values. …
Stansbury introduces judicial ethics bill on U.S. Supreme Court steps

Stansbury introduces judicial ethics bill on U.S. Supreme Court steps

U.S. Rep. Melanie Stansbury announced a bill on Thursday that would, if enacted, establish judicial ethics to the U.S. Supreme Court. The Judicial Ethics…
Latest SCOTUS abortion case uncertain and could impact New Mexico

Latest SCOTUS abortion case uncertain and could impact New Mexico

The U.S. Supreme Court heard oral arguments on Wednesday on an abortion-related case, this time over whether an Idaho anti-abortion law preempts a federal…
Abortion fund provider rebrands and holds open house

Abortion fund provider rebrands and holds open house

An abortion fund provider unveiled a rebrand and offered an open house in Las Cruces to celebrate the organization’s new name, mission and values. …
Politics and abortion, how much will it matter?

Politics and abortion, how much will it matter?

At the national level, abortion is still a high-stakes issue with both major presidential candidates talking about it in their campaigns, but it may…
Progressives going after incumbents in hot Democratic primaries

Progressives going after incumbents in hot Democratic primaries

By Justin Horwath, NM In Depth It’s a safe bet Democrats will barrel into 2025 with their supremacy intact at the New Mexico Legislature.…
Effort to challenge six laws enacted last year comes to an end

Effort to challenge six laws enacted last year comes to an end

Earlier this month, the New Mexico Supreme Court denied and dismissed the effort to challenge six laws enacted in 2023. The New Mexico Supreme…
Vasquez calls out Republicans for ‘inaction’ on border policy

Vasquez calls out Republicans for ‘inaction’ on border policy

U.S. Rep. Gabriel “Gabe” Vasquez, a Democrat who represents the state’s 2nd Congressional District along the U.S.-Mexico border, cosponsored a resolution on Monday calling…
Nuclear Watch New Mexico calls for comprehensive plutonium cleanup at LANL

Nuclear Watch New Mexico calls for comprehensive plutonium cleanup at LANL

A group of anti-nuclear activists used data from Los Alamos National Laboratory to map places where plutonium contamination has been found in areas near…
Latest SCOTUS abortion case uncertain and could impact New Mexico

Latest SCOTUS abortion case uncertain and could impact New Mexico

The U.S. Supreme Court heard oral arguments on Wednesday on an abortion-related case, this time over whether an Idaho anti-abortion law preempts a federal…
Ozone pollution continues to plague New Mexico

Ozone pollution continues to plague New Mexico

Four of the nine New Mexico counties evaluated in the annual State of the Air report received failing marks for ozone pollution. The counties…

GET INVOLVED

© 2023 New Mexico Political Report